Holland Wire Mesh installation method:
Due to the installation of the Holland Wire Mesh, the columns need to be pre embedded. Therefore, it is necessary to dig a 30-50 cm pit in advance, and dig one every 3 meters, as the columns are made every 3 meters. According to the terrain, the Gewen site column can be selected.
After digging the pit, fasten the column cap on the column, place it in the pit, and fix it with cement. It will take about 48 hours to fix it.
Once the column is fixed, you can install the Holland Wire Mesh. Secure the Holland Wire Mesh with the column using a buckle, with one at approximately 30 centimeters of the buckle.
Just like this, all the installation is done!

Contact Us
Cel:+86-18632891888
Tel: +86-318-7756166 7756996
Fax: +86-318-8556699
Emali: sales@kanglianwiremesh.com
New Factory Add: 800 meters from Northern of Qianpu Village,West Liangwa Town, Anping County, Hebei Province.
About Us

We warmly welcome domestic and foreign customers to visit our factory. Sincerely hope to build up good business relationship with you on the basis of mutual benefit and create a better future together.
 Home | About Us | Feedback | Contact Us | map  Copyright © Hebei Kanglian Road Traffic Safety Facilities CO.,Ltd.